New Build Report attributing responsibility to the...

Expert Report for Construction Company due to Parquet Defects in New Development

The buyer of a new-build home detected serious defects in the installed parquet, with widespread lifting and delamination during the first heating season.

Client
New-build buyer
Delivery time
40 days
Jurisdiction
Civil · Barcelona
Result
Report attributing responsibility to the subcontracted installation company
§ The case, step by step
01

The assignment

The buyer of a new-build home detected serious defects in the installed parquet, with widespread lifting and delamination during the first heating season.

02

The technical investigation

Inspection of the installed parquet, measurement of ambient and substrate moisture, analysis of the heating system installation and comparison against the specifications.

03

The expert report

The report evidenced the incompatibility between the installed heating system and the parquet type specified, constituting a design and execution defect.

04

The outcome

The developer replaced the parquet in full and revised the heating system within the statutory LOE periods.

Standards and techniques applied
Construction CompaniesPathologiesNew ConstructionClaims